MiSpeL in apartment buildings: time-of-use tariffs with battery storage in practice
Since MiSpeL, storage may mix solar and grid power without losing EEG funding. What this means for apartment buildings with PV and a time-of-use tariff.
In short: Until now, the rule was: if a battery storage system charges even a single kilowatt hour from the grid, the solar power fed into the grid loses its entitlement to EEG funding. With its determination on the “Market Integration of Storage and Charging Points”, MiSpeL for short, the Bundesnetzagentur (Federal Network Agency, BNetzA) adopted on 1 October 2026 the rules under which solar and grid electricity in the same storage system are accounted for separately and cleanly. For apartment buildings, this means: a storage system can absorb solar power during the day and charge low-cost grid electricity at night – and use both economically.
The problem so far: green or grey, but not both
The EEG (Renewable Energy Sources Act) funds electricity from renewable sources. A storage system that buffers solar power was therefore unproblematic – as long as it charged solar power exclusively. This so-called exclusivity principle had a harsh consequence: if the storage system was also charged from the grid, it was no longer possible to distinguish which kilowatt hour was “green” and which was “grey”. The solar power fed into the grid then lost its entitlement to funding.
For storage operators, this was a choice between two worlds:
- Charge solar power only and keep the funding – but the storage system then often stays empty on overcast days and in winter.
- Also charge grid electricity, for example at night at low prices – but risk the funding for the solar power.
Particularly with dynamic and time-variable tariffs, this is unsatisfactory: the economically best schedule often charges both.
What MiSpeL changes
With the Solarspitzengesetz (Solar Peak Act), the legislator created two further routes in the EEG in 2025 alongside the exclusivity principle and empowered the BNetzA to determine the details. It has done so with MiSpeL (Market Integration of Storage and Charging Points):
| Option | How it works | For whom |
|---|---|---|
| Metering-based allocation option | Solar and grid electricity are separated arithmetically on the basis of quarter-hourly metered values using fixed formulas. As a rule, two meters are required for this; in special cases, one is sufficient. | open to all operators |
| Flat-rate option | A fixed share of the electricity fed into the grid is deemed eligible for funding on a flat-rate basis. | intended for small solar installations; additionally requires state aid approval from the EU |
This allows storage systems to run in mixed operation: funding and relief are retained proportionally for the share that demonstrably comes from renewable generation.
Further points of the determination:
- Charging points too: MiSpeL applies not only to stationary storage systems but also to bidirectional charging points – an electric car that feeds power back is treated like a storage system.
- Not only for funded installations: The rules can also be used with non-funded installations and even without own generation.
- Levies: Grid electricity that is stored temporarily and later fed back into the grid can be relieved of levies through netting under the Energiefinanzierungsgesetz (EnFG, Energy Financing Act).
- Grid charges are not covered by MiSpeL. Storage systems commissioned by August 2029 are exempt for 20 years from grid charges on temporarily stored electricity under § 118(6) EnWG (Energy Industry Act); for new storage systems from 2029, the AgNes reform provides for a separate capacity price.
When does this apply?
- 1 October 2026: decision adopted by the BNetzA
- 7 October 2026: publication in the official gazette; according to law firms, in force since 21 October 2026
- Until the end of September 2027: transition period. During this time, the two new options can be used if the grid operator and the metering point operator agree.
Anyone planning now should therefore talk to the grid operator and metering point operator early on and agree on the metering concept.
What this looks like in an apartment building
A typical setup: PV on the roof, a battery storage system in the basement, residents who use the solar power – via tenant electricity or communal building supply (GGV) – and a tariff with low-cost and expensive time windows.
A day in MiSpeL mixed operation then runs like this:
- At night, the storage system tops up at low grid electricity prices when the schedule expects little sun for the following day.
- In the morning, the storage system covers the peak when residents shower, cook and electric cars are still plugged in.
- At midday, the storage system absorbs solar power instead of feeding it into the grid at low prices.
- In the evening, it discharges during the expensive evening peak – with solar power from midday.
Without MiSpeL, step 1 would have jeopardised the funding for the solar power fed into the grid. With the metering-based allocation option, every quarter hour is allocated cleanly.
What it takes
A suitable metering concept. As a rule, the metering-based allocation option requires two meters that deliver quarter-hourly values. In an apartment building, the residents’ meters and, where applicable, a summation meter are added. The concept should be agreed with the metering point operator before installation.
A control system that creates schedules. For the storage system to charge and discharge at the right time, forecasts for generation and consumption as well as the tariff prices are needed. An energy management system uses these to create the schedule and adjusts it continuously.
Clean data for billing. Which quantities were green and which were grey must be documented traceably – for funding, levies and billing with the residents.
Coordination with the grid operator. During the transition period until September 2027, the grid operator’s consent is a prerequisite.
What Apollo takes care of
Apollo EMS and Apollo OS control storage, PV and charging points in apartment buildings: with schedules based on the time-of-use tariff, self-consumption optimisation and arbitrage. The metered values for each quarter hour are available for allocation and billing. Find out more under Energy management – or contact us directly.
Frequently asked questions
What does MiSpeL mean?
MiSpeL stands for “Marktintegration von Speichern und Ladepunkten” (Market Integration of Storage and Charging Points). It is a determination by the Bundesnetzagentur that governs how electricity from storage systems and bidirectional charging points is split between green electricity eligible for funding and grid electricity.
May my storage system now charge grid electricity without me losing the EEG funding?
With the metering-based allocation option, yes: the funding is retained proportionally for the solar power. During the transition period until the end of September 2027, the grid operator and the metering point operator must agree.
Do I need new meters?
For the metering-based allocation option, as a rule, yes – usually two meters with quarter-hourly values. Exactly which meters are required depends on the metering concept.
Does MiSpeL reduce my grid charges?
No. MiSpeL governs EEG funding and relief from levies, not grid charges. For storage systems commissioned by August 2029, the grid charge exemption under § 118(6) EnWG applies for this.
Does this also apply to my electric car?
For bidirectional charging points, yes: under MiSpeL they are treated like storage systems.
Sources
- Bundesnetzagentur: Festlegungsverfahren zur Marktintegration von Speichern und Ladepunkten (MiSpeL) (German)
- Bundesnetzagentur: Festlegung zur Marktintegration von Speichern und Ladepunkten (German)
- Bundesnetzagentur: Pressemitteilung zum Beschluss der MiSpeL-Festlegung (German)
- pv magazine: Bundesnetzagentur beschließt MiSpeL-Regeln für Speicher und bidirektionales Laden (01.10.2026) (German)
- Prometheus Rechtsanwälte: Update: „Dornröschen tanzt“ – MiSpeL-Festlegung (German)
As of November 2026. This article does not replace legal advice; the determination of the Bundesnetzagentur (ref. 618-25-02) and its annexes are authoritative.